General Features:
-> DEF: series of production equipment used to make non reversible chemical-physical transformation of materials through a fixed technological routing.
-> CHAR:
- Fixed/ obliged technological routing;
- Trasformations are non reversible;
- Sectors: Petrochemical, oil refineries, cement, glass, rubber, paper production.
- Products are mainly uses in secondary industrieseeeeeee
-> MODELS:
- Work load model;
Example: Cement
-> DEF: hydraulic binder.
- Can be mixed with water and poured to set as a solid mass or use ingredient in making mortar or concrete.
-> MANUFACTURE:
- DRY PROCESS: raw materials are ground and dried to raw meal in the form of a flowable powder. The dry raw meal is fed to the preheater or precalciner kiln or, more rarely, to a long dry kiln.
- SEMI-DRY PROCESS: the dry raw meal is pelletised with water and fed into a grate preheater before the kiln or to a long kiln equipped with crosses.
- SEMI-WET PROCESS: the slurry is first dewatered in filter presses. The resulting filter cake is extruded into pellets and then fed either to a grate preheater or directly to a filter cake dryer for raw meal production
- WELT PROCESS: the raw materials (often with a high moisture content) are ground in water to form a pumpable slurry. The slurry then is either fed directly into the kiln or first to a slurry dryer.
FLOW SHEET CEMENT MANUFACTURING: | ASME PROCESS DIAGRAM |
Physical flow:
-> Raw materials are converted to Finished Products through production stages
-> CHAR of innovative plants:
- Capital expensive: Big systems, based on big investment (to achieve the economies of scale);
- Economy of scale;
- Automatization (machinaries are controlled by disance;
- Relevance of technological parameters of the production process (temperatures, pressures, …);
- Significant investment in sensors, equipment control, etc;
- Control often automated with supervisory intervention.
- Simple production logistics: for natural consequences of fixed technological routing.
-> Pipelines (operate in continuous & discontinuous flow) are based in serial transporters;
-> Are designed into the plant structure;
-> Products have few variants and may require few materials within the product recipe;
- Simple production management: Management decision al limited to two main problems; batch sizing (is the number of production campaigns) + batch sequencing.
- High plant utilization and equipment efficiency:
-> High production volumes + Stable volumes through time => economically-reasonable investment.
-> Economies of scales can be better achieved with higher plant sizes.
-> Batch Process: more inefficients are du e to the inherent characteristics of this type of production.
- Low need for workforce;
- Qualitative characteristics of products stable.
- Low flexibility:
-> Limited set of products, batch wise production: due to batch sizing and sequencing;
-> Plats are not easily reconfigured/ re convertion.
- High risk of obsolescence: facility lifetime is related to products lifetime.
- Significant impact of failures: there are some degree of parallelization/ reducancy but not much. It depends on the type of production: batches 🔻 criticla; continuous 🔺 critical.
- Importance of variations in process conditions.
Kynd of plants:
-> Plants are designed to operate:
- CONTINUOUS FLOW production process: materials are moved continously through the production equipement of the plant;
- BATCH PRODUCTION process: materials are processed as batches (is discontinuous transformation thanks to storages).
-> Logically speaking are the same, but physically are different (continuous and batch productions).
đź“Ś SEVESO LAW: is the European Law that impose that only chemical engineer can design chemical plants.
- Tha name was taken by the Seveso that was fill up by pollution from a chemical plant that was destroied.
Continuous Flow:
-> TECHNOLOGICAL ROUTING: it’s lead to identify all the production equipment types that are needed and, amongst them, the bottleneck.
- APC calculated considering typical losses;
- APC and demand are compared to verify the design choices.
-> STEPS:
- Steps 1 – 2 basically these are dependent on the knowledge of the process (e.g. chemical engineers) and the subsequent constraints; an industrial engineer can basically understand but it is dependent on the technological options available on this side, and constraints;
- Step 3 – 4 once he/she has understood, the industrial engineer can basically support the study of the plant structure, starting from the bottleneck, in order to calculate the APC > Hence, (understood the process constraints) a first clear indication is available on the bottleneck for the production flows > TPC is known > therefore an evaluation of APC based on SR and A (concepts of coefficient losses).
- Step 4 remember the fact that the SR may be dependent on the process constraints -> if we do not operate at standard process conditions (i.e. either warm-up or different conditions from process conditions at the nominal / standard regime), the SR may be a different value, respect to the best value;
- Step 5 few options may be available, for ex. duplicating some equipment but this should be clearly verified with knowledgeable engineers on the process.
Rough Design:
- Define the production flows according to the technological routing required for the product
- Identify all the production equipment types that are needed and the bottleneck
- Define the theoretical production capacity
where
- TPC = theoretical production capacity in [ton/hour], or other similar units, i.e. [kg/hours]
- Calculate the actual production capacity
where
- A = line availability (0 < A 1)
- SR = scrap rate (0 SR < 1) (varying according to the process conditions kept in the system)
- Compare the actual production capacity and the demand. If necessary, modify the line and go back to step 2
-> EXAMPLE:
Batch Process:
-> TECHNOLOGICAL ROUTING: leads to identify all the production equipement types that are needed.
- Yearly workload and # of available hours Nhi and Ahi are calculated for each type of production equipment i, considering all typical losses.
- # of production equipment of type i Nmi necessary to produce the production mix is then calculated.
-> CHAR:
- Batches of different products can be concurrently produced in the differen equipment.
- More intermittent management cycle: each equipment may be producing, in different campaigns, different products.
(We can produce differnt type of nylon in the same time).
- đź”˝ VOLUME => đź”˝ productivity.
- Mid flexibility & mid range production mix.
- Similar to job shop (logially, physically are very different).
-> STEPS:
- Steps 1 – 2: basically these are dependent on the knowledge of the process (e.g. chemical engineers) and the subsequent constraints; an industrial engineer can basically understand but it is dependent on the technological options available on this side, and constraints;
- Step 3 – 4: once he/she has understood, the industrial engineer can basically support the study of the plant structure, starting from the bottleneck, in order to calculate the APC > Hence, (understood the process constraints) a first clear indication is available on the bottleneck for the production flows > TPC is known > therefore an evaluation of APC based on SR and A (concepts of coefficient losses).
- Step 4: remember the fact that the SR may be dependent on the process constraints -> if we do not operate at standard process conditions (i.e. either warm-up or different conditions from process conditions at the nominal / standard regime), the SR may be a different value, respect to the best value;
- Step 5: few options may be available, for ex. duplicating some equipment but this should be clearly verified with knowledgeable engineers on the process.
Rough Design:
-> ASSUMPTIONS:
- Equipment are used according to Batch wise processing approach: to change from one to another is required a setup for the new campaign;
- Setup time are required and do not depend on the productio (batch) sequences.
-> STEPS:
- Identify the production mix
- Define the production flows according to the technological routing required for the products (in the production mix)
- Identify all the production equipment types that are needed
- Calculate yearly workload and number of hours available for each type of production equipment i
- Calculate the number of production equipment of type i necessary to produce the production mix
đź“Ś There is a production mix (within a limited range) considering that some functional departments can be identified.
Number Hours:
=> Yearly workload NH_i for production equipement i:
Where:
- i: index of the equipment-type;
- j: index of the product-type;
- N: number of different product-types.
- NC_j: Number of campaign of product-type j [batches/year];
- SR: Scrape Rate, percentage of materials out of tollerance;
- A: Availability, percentage ot up time (intervals), when the machines is required for production and actually available to work with respect to the total time (up time + down time).
- TPC: production capacity for a given equipment i, supporting the chemical-physical transformation of product j at a given step in its routing;
- STT_ij: setup time [hours/setup] (hours better and pratical measure);
-> HC is not considered: there is no clear machine interference problem as the manufacturing case and the intervention on the production equipment is clearly possible for a shutdown (maintenance).
-> NH consider also the presence of time losses within the machine calendar time
-> One campaign is coincident with one product batch;
Annual Hours:
-> # of hours available for each type of production equipment i
Number Product Equipment:
-> Number of production equipment of type i necessary to produce the production mix:
Evaluate the Yearly Costs:
- Overall plant costs: include costs of al the production equipment acquired to build the plant;
- m: coefficient used to split costs on plant/facility lifetime;
- Overall operation costs: may include different types of cost (energy costs, maintenance, raw material)
-> EXAMPLE:
-> AUTOCLAVE: bigo oven where the material is cooked continuously.
Oh my gοodness! Imрressive article dude! Thank you so
much, However I am encountering problems with your
RSS. I don’t know why I cannot subscribe to it. Is there anybody elsď˝… getting thе same RSS issues?
Anybody who knows the solution can you kindly respond?
Thanx!!
Hi, we don’t have RSS, but we’re working on it!